sa¹ú¼Ê´«Ã½

Skip to content
Join our Newsletter

Coastal GasLink fined again for sediment, erosion in pipeline work

VICTORIA — The company that is building a natural gas pipeline across northern British Columbia has been fined for a third time as a result of failure to comply with the requirements of its environmental assessment certificate. The sa¹ú¼Ê´«Ã½
20230125190156-63d1d066c212a0f1a9805966jpeg
The terminus for the Coastal GasLink natural gas pipeline is seen at the LNG sa¹ú¼Ê´«Ã½ export terminal under construction in Kitimat, sa¹ú¼Ê´«Ã½, on Wednesday, September 28, 2022. The company that is building a natural gas pipeline across British Columbia has been fined for a third time for not following the requirements of its environmental assessment certificate. THE CANADIAN PRESS/Darryl Dyck

VICTORIA — The company that is building a natural gas pipeline across northern British Columbia has been fined for a third time as a result of failure to comply with the requirements of its environmental assessment certificate. 

The sa¹ú¼Ê´«Ã½ government issued a bulletin saying Coastal GasLink has been fined $213,600 for "continued deficiencies with erosion and sediment control measures." 

The bulletin issued Wednesday says recurring issues with erosion and sediment control have resulted in ongoing compliance and enforcement action, though more recent inspections have shown improvement. 

The Environmental Assessment Office says more than 50 inspections have been done along the pipeline construction route since the project started in 2019, resulting in 37 warnings and two other financial penalties imposed last year: $72,500 in February and $170,100 in May. 

The office says it entered into a compliance agreement with Coastal GasLink last July that takes a more proactive approach to erosion for about 100 kilometres of the 670-kilometre pipeline route where ground had yet to be broken. 

The pipeline, which is in its final scheduled year of construction, is to connect natural gas facilities in northeastern sa¹ú¼Ê´«Ã½ to the LNG sa¹ú¼Ê´«Ã½ terminal in Kitimat, on the northern coast.

Coastal GasLink says the penalty reflects concerns about erosion and sediment control from inspections by the Environmental Assessment Office in February 2022, and the determination is "a reminder of how far we’ve come in a year."

"We continue to work closely with our regulators to look for ways where we can do better across our project, especially with erosion and sediment control," the company said in a statement.

This report by The Canadian Press was first published Jan. 25, 2023. 

The Canadian Press