sa国际传媒

Skip to content
Join our Newsletter

Broadway Subway鈥檚 revised service date disappears from project reports

Total project completion was last listed as being March 30, 2026
broadwaydisruption028-cc-56
Broadway Subway line construction captured earlier this year. The project is expected to be complete in early 2026

The Broadway Subway project continues to forecast that it will stay within its $2.83 billion budget, but the revised completion and service dates have been omitted from monthly reports.

In the June project status report from Transportation Investment Corp., schedule topped the list of five “yellow light” items on the project delivery dashboard that required near-term action. The extension of SkyTrain’s Millennium Line already announced a delay last November from late 2025 to early 2026.

“The start of piling activities was delayed at some construction locations. Recovery measures have been implemented by Broadway Subway Project Corp. (BSPC) and are being monitored closely,” said the most-recently released report. “A five-week concrete supplier strike in June 2022 delayed the completion of the base slab at Great Northern Way, which impacted the start of tunnel boring. As a result, project completion has moved from late 2025 to early 2026.”

The report for last October included the previous schedule, which targeted substantial completion for Nov. 27, 2025, service commencement on Dec. 27, 2025 and total completion Feb. 28, 2026. The reports from November through February showed the target for substantial completion had been postponed until Jan. 8, 2026, service commencement to Feb. 7, 2026 and total completion to March 30, 2026.

Beginning with the April status report, the dates were omitted and the red flag project schedule icons moved slightly to the right.

The project reported spending $32.5 million in June for a total of $1.18 billion to date, including $382.7 million from the federal government so far and $100.3 million from the City of Vancouver.

The five-kilometre subway and 700-metre elevated guideway will connect six underground stations from Great Northern Way-Emily Carr to Arbutus.

The report said there were six non-conformity reports in June about health and safety issues and construction quality processes. Of the 319 such reports during the project, 291 files were closed and 28 remained open.

The project reported a lost time injury frequency rate of 0.21 to date, less than the 2021 WorkSafeBC rate of 0.90 for heavy construction.

Schedule was one of the five project dashboard items assigned a yellow light ranking. The remaining six were all green lights. None was red, which would have denoted requiring immediate action to resolve.

Notes within the dashboard said discussions were progressing with sa国际传媒 Infrastructure Benefits, the Crown corporation in charge of hiring and supplying unionized workers, about workforce and permitting requirements. Discussions were also ongoing with developer PCI, and with TransLink and sa国际传媒 Line about integration with their systems. Targets had been achieved for Indigenous contracting, but discussions continued about project agreements and Indigenous art and cultural recognition at stations.

The second tunnel boring machine, nicknamed Phyllis, for Girl Guides of sa国际传媒 founder Phyllis Munday, broke through at Broadway-City Hall Station in late May. The June report said both tunnel boring machines were at the site under Cambie and Broadway.

BSPC is the design/build joint venture between Acciona of Spain and Ghella of Italy. Acciona is also working on the Site C dam and Pattullo Bridge projects.

In early 2022, Metro Vancouver fired Acciona from the $1.058 billion North Shore Wastewater Treatment Plant in North Vancouver over project delays, sparking duelling lawsuits filed in sa国际传媒 Supreme Court.