TransLink has announced that service between Bridgeport and Brighouse stations will once again be ending early at 9:30 p.m. from Monday to Friday as crews continue to work on the new Capstan Station.
Workers will be working on the station roof and platform to install tiling and signage, as well as integrate the station with the existing track.
The disruptions will start on Sept. 5 and end on Dec. 19, with regular service resuming on Dec. 20. Service between Bridgeport and YVR stations is unaffected.
Extra buses will stop at stations between Bridgeport and Brighouse every 10 minutes.
The $52 million Capstan Station was set to open later this year but has been delayed until early 2024 due to a .